On 30 October 2026, the Gujarat Electricity Regulatory Commission (GERC) published the Grid Interactive Distributed Renewable Energy Sources (DRES) Regulations, 2026 (Notification No. 11 of 2026) in the Gujarat Government Gazette…

The short answer

Systems commissioned on or after 30 October 2026 follow GERC DRES Regulations, 2026, with five routes: Net Metering and Net Billing (1–1,000 kW AC), Group Net Metering (6–1,000 kW AC), Virtual Net Metering (10–4,000 kW AC), and Gross Metering (6–4,000 kW AC). Homes keep 100% billing-cycle adjustment, zero banking charges, and a ₹2.25/kWh surplus rate. Non-residential adjustment is capped at 30% of grid imports per billing cycle.

Key takeaways

What GERC notified on 30 October 2026

On 30 October 2026, the Gujarat Electricity Regulatory Commission (GERC) published the Grid Interactive Distributed Renewable Energy Sources (DRES) Regulations, 2026 (Notification No. 11 of 2026) in the Gujarat Government Gazette Extraordinary. The notification repeals Gujarat's 2016 net-metering regulations for all new systems commissioned on or after that date and replaces them with five metering routes across MGVCL, DGVCL, UGVCL, PGVCL, and Torrent Power.

The short answer

For systems commissioned on or after 30 October 2026, GERC DRES Regulations, 2026 introduces five mechanisms: Net Metering (1–1,000 kW AC), Net Billing (1–1,000 kW AC), Group Net Metering (6–1,000 kW AC), Virtual Net Metering (10–4,000 kW AC), and Gross Metering (6–4,000 kW AC). Residential net-metering users keep 100% billing-cycle adjustment, zero banking charges, and a ₹2.25/kWh surplus purchase rate, or such rate as the Commission may specify (credited to bank within 30 days after financial year-end). By contrast, non-residential net-metering adjustment is capped at 30% of grid imports per billing cycle with banking charges and lapse of excess exports. Systems commissioned earlier remain under their existing regulations and agreements.

Key takeaways

Why the 30 October 2026 Gazette matters in Vadodara, Ahmedabad, Surat and Bharuch

Earlier guides on this site — including our 2016–2025 GERC summary — covered the 2016 regulations when the 2026 framework was still a May 2026 draft. With Notification No. 11 of 2026 now notified in the Official Gazette (Part IV-C, 30 October 2026), any new rooftop plant commissioned from November 2026 onward across MGVCL, DGVCL, UGVCL, PGVCL, or Torrent Power is governed by these updated clauses.

What did not change is PM Surya Ghar central CFA: central residential subsidy (₹30,000/kW for the first 2 kW, ₹18,000 for the 3rd kW, up to ₹78,000 subject to eligibility and DCR modules) and the Gujarat 22 October 2026 state top-up up to 2.18 kWp (for eligible systems commissioned on or after 22 October 2026, with a three-year expansion lock) remain MNRE and Government of Gujarat subsidy windows, separate from GERC's grid-accounting rules.

All five metering options compared

Under Regulation 4.3 and Regulation 8 of Notification No. 11 of 2026, eligible consumers across all categories can choose one metering mechanism per service connection:

Metering mechanismAllowed AC capacityWho it suitsKey accounting rule
Net Metering (NM)1 kW to 1,000 kW (1,250 kWp DC)Homes; C&I roofs with high daytime loadHomes: 100% set-off + ₹2.25/kWh surplus (or Commission-specified rate). Non-residential: 30% import cap + banking charges
Net Billing (NB)1 kW to 1,000 kW (1,250 kWp DC)Consumers preferring separate export creditOn-site self-consumption first; exports valued at GERC generic tariff against import bill
Group Net Metering (GNM)6 kW to 1,000 kWOne owner with multiple connections in the same name & tariff category15-minute time-block allocation across same-DISCOM connections by agreed ratio
Virtual Net Metering (VNM)10 kW to 4,000 kWMultiple consumers in the same tariff category & DISCOM (different names allowed)Entire generation exported and allocated by agreed ratio on 15-minute blocks
Gross Metering (GM)6 kW to 4,000 kWLarge roofs exporting 100% of powerFull generation sold to DISCOM at generic tariff; imports billed at retail tariff

Source: GERC DRES Regulations, 2026, Notification No. 11 of 2026, Regulations 4.3, 8, and 9.

Notice an important shift from the May 2026 draft: in the final Gazette text, Virtual Net Metering starts at 10 kW AC (not 100 kW AC as the earlier draft proposed), and Group Net Metering starts at 6 kW AC. That makes both options far more accessible to housing societies, multi-meter residential compounds, and multi-branch businesses within the same DISCOM licence area.

Residential vs non-residential net metering (Reg 9.1.5)

Regulation 9.1.5 draws a sharp line between residential prosumers and every other category:

Group Net Metering vs Virtual Net Metering: what societies and families need to know

Both GNM (≥ 6 kW AC) and VNM (≥ 10 kW AC) allocate exported electricity across participating meters on a 15-minute time-block basis using an allocation ratio fixed in the DISCOM agreement (adjustable once a financial year with 30 days' advance notice).

Connectivity fees, 6 kW strengthening and the new BESS rule

Three practical cost and technical thresholds sit in Regulations 4.9, 6.2, 6.4, and Annexure-I:

  1. Deemed feasibility ≤ 10 kW (Reg 6.2): Complete applications up to 10 kW are deemed accepted without a technical feasibility study, with commensurate sanctioned-load enhancement carried out by the DISCOM.
  2. Connectivity fees (Annexure-I): Non-refundable connectivity fees are listed as ₹1,500 (1–6 kW), ₹10,000 (>6–100 kW), and ₹50,000 (>100 kW to 1 MW/4 MW) per connection. Check your DISCOM estimate for how the Government of Gujarat ₹2,950 residential waiver (up to 6 kW) interacts on your live bill estimate.
  3. System strengthening above 6 kW (Reg 6.4): Up to 6 kW aggregate capacity, distribution strengthening stays inside the utility's Annual Revenue Requirement (zero strengthening fee to the consumer). Above 6 kW up to 150 kW LT, state DISCOMs and Torrent Power recover 25% of approved per-kW LT load-release charges on the capacity exceeding 6 kW.
  4. BESS requirement above 100 kW demand (Reg 4.9): If your contract demand exceeds 100 kW and you install DRES capacity above your contract demand (under NM, GNM, NB, or non-residential VNM), the excess capacity is allowed only if you include a BESS capable of at least 2 hours of daily charge/discharge for at least 50% of that excess capacity.

Next step

If you are planning a residential, society, or multi-meter rooftop plant in Vadodara, Ahmedabad, Surat, Bharuch, or anywhere in Gujarat, WhatsApp your latest DISCOM bill to +91 96248 66799 (or call +91 96248 66799) or write to info@uvrgreenenergies.com via contact to book a site survey. UVR Green Energies checks your tariff category, sanctioned load, and 15-minute consumption pattern before recommending Net Metering, Net Billing, GNM, or VNM.

Frequently asked questions

Does GERC DRES Regulations 2026 affect existing solar plants in Gujarat?

No. Regulation 4.1 states that the 2026 regulations apply to DRES installations commissioned on or after notification (30 October 2026). Plants commissioned earlier remain governed by the earlier regulations, orders, and interconnection agreements under which they were commissioned.

What is the minimum size for Virtual Net Metering and Group Net Metering in Gujarat?

Under Regulation 4.3 of Notification No. 11 of 2026, Group Net Metering requires a minimum capacity of 6 kW AC (maximum 1,000 kW AC), while Virtual Net Metering requires a minimum of 10 kW AC (maximum 4,000 kW AC). Ordinary Net Metering and Net Billing start at 1 kW AC.

Do Gujarat homeowners still get ₹2.25 per unit for surplus solar under the 2026 rules?

Yes. Under Regulation 9.1.5, residential net-metering prosumers receive 100% billing-cycle adjustment with no banking charges, and leftover surplus is deemed purchased at ₹2.25 per kWh (or such rate as GERC specifies from time to time), with any financial-year-end credit balance paid into the consumer's bank account within 30 days.

Why does the 30% adjustment cap matter for commercial and industrial roofs in Gujarat?

Under Regulation 9.1.5, non-residential net-metering consumers can offset only up to 30% of the electricity they draw from the grid during a billing cycle, and pay banking charges. Exports above that 30% cap lapse without compensation, making daytime self-consumption sizing critical for offices and factories.

When do residential users need a battery (BESS) under GERC DRES 2026?

Typical residential rooftops do not trigger the mandatory BESS rule. Regulation 4.9 requires a BESS only when a prosumer has contract demand above 100 kW and installs DRES capacity exceeding that contract demand (and in Virtual Net Metering, that excess-capacity BESS proviso explicitly exempts the residential category).

Sources

  1. GERC (Grid Interactive Distributed Renewable Energy Sources) Regulations, 2026 — Notification No. 11 of 2026, Gujarat Government Gazette Extraordinary (30 October 2026)
  2. SolarQuarter — GERC Notifies 2026 Distributed Renewable Energy Regulations (2 November 2026)
  3. Energetica India — Gujarat Allows up to 4 MW Distributed RE Systems Under New Rules (2 November 2026)
  4. Adynta — GERC DRES Regulations 2026: Rooftop Solar Rules for Factories (13 November 2026)

Frequently asked questions

Does GERC DRES Regulations 2026 affect existing solar plants in Gujarat?

No. Regulation 4.1 states that the 2026 regulations apply to DRES installations commissioned on or after notification (30 October 2026). Plants commissioned earlier remain governed by the earlier regulations, orders, and interconnection agreements under which they were commissioned.

What is the minimum size for Virtual Net Metering and Group Net Metering in Gujarat?

Under Regulation 4.3 of Notification No. 11 of 2026, Group Net Metering requires a minimum capacity of 6 kW AC (maximum 1,000 kW AC), while Virtual Net Metering requires a minimum of 10 kW AC (maximum 4,000 kW AC). Ordinary Net Metering and Net Billing start at 1 kW AC.

Do Gujarat homeowners still get ₹2.25 per unit for surplus solar under the 2026 rules?

Yes. Under Regulation 9.1.5, residential net-metering prosumers receive 100% billing-cycle adjustment with no banking charges, and leftover surplus is deemed purchased at ₹2.25 per kWh (or such rate as GERC specifies from time to time), with any financial-year-end credit balance paid into the consumer's bank account within 30 days.

Why does the 30% adjustment cap matter for commercial and industrial roofs in Gujarat?

Under Regulation 9.1.5, non-residential net-metering consumers can offset only up to 30% of the electricity they draw from the grid during a billing cycle, and pay banking charges. Exports above that 30% cap lapse without compensation, making daytime self-consumption sizing critical for offices and factories.

When do residential users need a battery (BESS) under GERC DRES 2026?

Typical residential rooftops do not trigger the mandatory BESS rule. Regulation 4.9 requires a BESS only when a prosumer has contract demand above 100 kW and installs DRES capacity exceeding that contract demand (and in Virtual Net Metering, that excess-capacity BESS proviso explicitly exempts the residential category).

Sources

  1. GERC (Grid Interactive Distributed Renewable Energy Sources) Regulations, 2026 — Notification No. 11 of 2026, Gujarat Government Gazette Extraordinary (30 October 2026)
  2. SolarQuarter — GERC Notifies 2026 Distributed Renewable Energy Regulations (2 November 2026)
  3. Energetica India — Gujarat Allows up to 4 MW Distributed RE Systems Under New Rules (2 November 2026)
  4. Adynta — GERC DRES Regulations 2026: Rooftop Solar Rules for Factories (13 November 2026)

Keep reading